Manual laying work procedure

This procedure applies to projects done on streets, small esplanades or short stretches of road. On a daily basis, the transverse and longitudinal JRI+ joints are placed as per the concrete laying plan.

The next day or later, the concrete is poured with a pump, in the case of esplanades, or with concrete trucks, in the case of streets, and it is spread. The pouring of the concrete must be done on both sides of the transverse JRI+ seal to prevent lateral displacement.

During the following hours we proceed to cure with water avoiding to change in color of the concrete stopping cracks from appearing.  Specific concrete curing products can also be used.